说明:
Notes:
1.安装位置参见首页图F463S-J0301-01.
Installation site refers to F463S-J0301-01.
2.本安装图根据无锡电站辅机厂提供的300t/h除氧器及80M水箱安装图进行设计的.
3This drawing is drawed according to "300t/h deaerator and 80M tank installation
3drawing" supplyed by"Wuxi City Power Auxiliary Equipment Works".
3.设备安装前,应与来货核对无误后方可施工
.Before installationed, the equipment must be checked with this drawing.
4.除氧器支座找平与土建预留插筋焊牢,然后二次灌浆。
The deaerator pedestal will be levelled and securely welded with civil embeddedinserting rebars and then it will be placed with concrete for the second time.